How long does the install take?

On site work is one to two days. Day one is concrete pad, generator placement, gas and electrical connections, transfer switch. Day two, when needed, is commissioning, testing, and the walkthrough. The 30 to 90 day total timeline is dominated by permits and inspection scheduling with the city, not actual labor.